ARKA BRITTON SERVICES PRIVATE LTD. Vs CNH INDUSTRIAL (INDIA) PRIVATE LTD.
- Delhi High Court adapter: text extracted by Firecrawl; the source PDF was not retrieved, so no original file is archived.
%
IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on: 14.08.2026
Judgment pronounced on: 19.08.2026
CNR No. DLHC011315482018
O.M.P. (COMM) 268/2018
ARKA BRITTON SERVICES PRIVATE LTD. .....Petitioner
Through: Mr. Abhik Kumar & Mr. Dipak
Girdhar, Advs.
versus
CNH INDUSTRIAL (INDIA) PRIVATE LTD. .....Respondent
Through: Mr. Yamandeep Kumar & Ms.
Samiksha Goel, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
J U D G M E N T
The present petition is filed under Section 34 of the Arbitration
and Conciliation Act, 1996 (for short 'the Act') challenging the arbitral
award dated 14.02.2018 (for brevity 'the impugned award').
Brief facts are that the petitioner is a service provider, rendering
outsourced manpower and related services to the respondent since
year 2011. The respondent is engaged in the business of manufacture
and sale of tractors, other agriculture implements and machinery.
2.1 On 21.03.2014, the parties to the lis entered into two contracts,
namely WC/REV/146/14 (for short „146‟) for salary of outsource
services and WC/REV/147/14 (for short „147‟) for reimbursement of
outsource service expenses (collectively referred to as the „contracts‟).
As per clause 2 of both contracts, the duration of the contract was from 01.04.2014 to 31.03.2015, extendable on mutually agreed terms
in writing. Clause 11 of contract 146 and Clause 9 of contract 147
provided for termination/cession where under the contract could be
terminated by either party by giving thirty days written notice and if
not extended it would deemed to have expired after expiry of three
months.
2.2 The contract was set to expire on 31.03.2015 and vide e-mail
dated 16.03.2015, the respondent called upon the petitioner to submit
the proposal for the year 2015-16. Negotiations for execution of fresh
contracts continued during March-April, 2015. The respondent by an
email dated 05.05.2015 communicated the decision that both the
contracts are terminated.
2.3 The petitioner alleging that the termination is abrupt and illegal,
invoked arbitration by issuing notice dated 01.09.2015 as per clause
15 of both contracts. The respondent appointed the sole arbitrator vide
letter dated 11.09.2015.
2.4 Before the arbitrator, the petitioner raised thirteen claims
aggregating to Rs.5,48,04,402/-. The respondent raised a counter
claim of Rs.27,79,818/-. The arbitrator vide impugned award
concluded that the contract did not automatically expire on 31.03.2015
and stood extended by three months i.e., upto 30.06.2015. The
termination letter dated 05.05.2015 was held to be in breach of the
terms of the contract. The arbitrator awarded a sum of Rs.11,21,810/-
to the petitioner and a sum of Rs.27,40,066/- to the respondent. After
adjustments a net sum of Rs.16,18,256/- was awarded in favour of the respondent along with interest @ 12% per annum from the date of
award till the realization. Aggrieved of the award this petition is filed.
Learned counsel for the petitioner contends that the
appointment of the arbitrator is in violation of Section 12(5) of the Act
as amended vide Arbitration and Conciliation (Amendment) Act, 2015
(for short „2015 Amendment Act‟).
3.1 It is argued that the arbitrator failed to appreciate that the claims
towards salary and telephone/travel expenses pertained to
reimbursement for the period of April, 2015 to June, 2015. The
material on record was not properly appreciated, particularly that there
was no evidence adduced to establish that the employees were paid
through other agencies. The argument is that the findings recorded are
based on conjectures and surmises.
3.2 The contention is that the arbitrator erred in concluding that the
claims for recruitment cost and loss of credibility were non-arbitrable
and do not arise from the contract.
3.3 Lastly, the submission is that it was wrongly concluded that the
petitioner suffered no loss of business whereas the petitioner was
acting as ancillary to the respondent and had the employees not left,
the petitioner could have entered into other contractual engagements.
Per contra the impugned award is well reasoned and calls for
no interference. Reliance is placed upon Delhi Airport Metro Express
Pvt. Ltd. v. Delhi Metro Rail Corporation Ltd., (2022) 1 SCC 131 to
argue that a plausible view is taken in the impugned award and calls for no interference. The decision of the Supreme Court in Dyna
Technologies Pvt. Ltd. v. Crompton Greaves Ltd., (2019) 20 SCC 1 is
pressed into service to argue that the interference is warranted under
Section 34 of the Act only in case of perversity or a patent illegality
and not for existence of another possible view.
4.1 The contention that the appointment of the arbitrator was in
violation of Section 12(5) of the Act is controverted stating that the
arbitrator was appointed on 16.09.2015 and the amended provision is
not applicable.
Heard the learned counsel for the parties and perused the
relevant record with their able assistance.
The issue whether the amended Section 12(5) of the Act added
by the 2015 Amendment Act shall apply to the arbitration proceedings
commenced prior to amendment even though the award is delivered
after the amendment is no longer res integra. The Division Bench of
this court in DV Anand v. Hindustan Petroleum Corporation Ltd,.
2026 SCC OnLine Del 4903 after considering the decision in Ellora
Paper Mills Limited v. The State of Madhya Pradesh, (2022) SCC
OnLine SC 8 and relying upon the earlier Division Bench decision of
this court in Kamal Kumar v. Municipal Corporation of Delhi, 2023
SCC OnLine Del 6515 held that where the arbitral proceedings had
commenced prior to the insertion of Section 12(5) of the Act, the
amended provision shall not apply. The relevant paras read as under:
“62. On the other hand, the Hon‟ble Supreme Court in
Board of Control for Cricket in India (supra) and
Rajasthan Small Industries Corporation Ltd (supra),
clearly proceeded on the principle that where
arbitral proceedings had already commenced before
insertion of Section 12(5), the amended provisions
would not apply by virtue of Section 26 of the 2015
Amendment Act.
We may also note that a Division Bench of this
Court in Kamal Kumar v. Municipal Corporation of
Delhi 2023 SCC OnLine Del 6515 dealt with a
similar situation where arbitral proceedings had
commenced prior to the amendment though the
award itself was rendered subsequently. Relying
upon Rajasthan Small Industries Corporation Ltd
(supra), the challenge to the competence of the
arbitrator was rejected, holding that the 2015
Amendment Act would not invalidate proceedings
which had validly commenced before the
amendment came into force.
Thus, the legal position with respect to the
jurisdiction of the arbitrator being clear, we now
proceed to examine the facts of the present case.”
The arbitrator at the first instance considered the date when the
contracts expired. It was held that the contracts was not expressly
terminated and stood extended by three months i.e. up to 30.06.2015.
The relevant portion is quoted below:-
“19. In view of the above discussions I hold:
(i) That in view of the terms of the contracts in
question the contracts did not automatically
expire on 31.03.2015.
(ii) That the contracts having not been expressly
terminated, the terms (periods) thereof stood
extended by three months i.e. upto
30.06.2015.
(iii) That the closure of the contracts by
communication dated 05.05.2015 and given
effect to from 01.04.2015 is in breach of the
terms of the two contracts and is invalid and
ineffective.
Issues 1, 1a and 1b are answered accordingly.”
This issue is not in dispute in the present petition.
The petitioner claimed salary of the employees from April to
June, 2015 and reimbursement of travel/telephone expenses incurred
by the employees. The arbitrator proceeded under Section 73 of the
Contract Act, 1872 (for short „the Contract Act‟) for dealing with the
claim of damages for breach of contract. It was decided that the
petitioner successfully established breach of contractual terms by the
respondent. Finding of fact was recorded that the petitioner had
suffered no corresponding loss as the salary and telephone/travel
expenses were paid by the respondent to the employees and no
liability remained on the petitioner on this account. To similar effects
were findings with regard to service tax and education cess. The
damages for loss suffered by the petitioner due to non-receipt of
remuneration @8% of the salary component to be paid to the
employees for April to June, 2015 was quantified and granted.
It would be relevant to quote the following decisions of the
Supreme Court dealing with the principles governing award of
damages under section 73 of the Contract Act:-
9.1 The Supreme Court in Kailash Nath Associates v. DDA, (2015)
4 SCC 136 held:
“43.1. Where a sum is named in a contract as a
liquidated amount payable by way of damages, the
party complaining of a breach can receive as
reasonable compensation such liquidated amount only
if it is a genuine pre-estimate of damages fixed by both
parties and found to be such by the court. In other
cases, where a sum is named in a contract as a
liquidated amount payable by way of damages, only
reasonable compensation can be awarded not
exceeding the amount so stated. Similarly, in cases
where the amount fixed is in the nature of penalty, only
reasonable compensation can be awarded not
exceeding the penalty so stated. In both cases, the
liquidated amount or penalty is the upper limit beyond
which the court cannot grant reasonable compensation.
43.2. Reasonable compensation will be fixed on wellknown principles that are applicable to the law of
contract, which are to be found inter alia in Section 73
of the Contract Act.
43.3. Since Section 74 awards reasonable
compensation for damage or loss caused by a breach of
contract, damage or loss caused is a sine qua non for
the applicability of the section.
43.4. The section applies whether a person is a plaintiff
or a defendant in a suit.
43.5. The sum spoken of may already be paid or be
payable in future.
43.6. The expression “whether or not actual damage or
loss is proved to have been caused thereby” means that
where it is possible to prove actual damage or loss,
such proof is not dispensed with. It is only in cases
where damage or loss is difficult or impossible to
prove that the liquidated amount named in the contract,
if a genuine pre-estimate of damage or loss, can be
awarded.”
9.2 The Supreme Court in State of Rajasthan v. Ferro Concrete
Construction (P) Ltd. , (2009) 12 SCC 1 held:
“55.While the quantum of evidence required to accept
a claim may be a matter within the exclusive
jurisdiction of the arbitrator to decide, if there was no
evidence at all and if the arbitrator makes an award of
the amount claimed in the claim statement, merely on
the basis of the claim statement without anything more,
it has to be held that the award on that account would
be invalid. Suffice it to say that the entire award under
this head is wholly illegal and beyond the jurisdiction
of the arbitrator, and wholly unsustainable.”
From the above decision, the picture emerges is of the twin
conditions required to be fulfilled for awarding liquidated damages
under Section 73 of the Contract Act. First, breach of the contractual
conditions and second, the actual loss or damage suffered or the proof
that it is not possible to prove the actual damage suffered. In the case
in hand, the actual loss suffered was not proved by the petitioner
rather the finding recorded is that the salary and telephone/travel
expenses were not borne by the petitioner, as a natural consequence
the claim was rightly rejected.
The contention of learned counsel for the petitioner that it was
not proved that the respondent had actually paid the salary and
telephone/travel expenses to the employee is misconceived. The
petitioner had to prove the loss suffered due to breach of contract by
the respondent and the petitioner failed to discharge the onus.
The challenge to the rejection of the claims on account of loss of recruitment fee, damage for loss of creditability and loss of
business lacks merit in view of the undisputed findings recorded by
the arbitrator. It is recorded that there was no pleading of claims made
in the statement of claim and clauses of both the contracts had no
mention of recruitment fee. The arbitrator rightly held that the claims
did not arise from the contract and were non-arbitrable. It was
concluded that the contractual arrangement operated on „collect and
pay‟ basis whereby the respondent had to at the first instance pay the
estimated salary and telephone/travel expenses and the petitioner had
to disburse the dues to the employees. After the payment of salary,
telephone/travel expenses by respondent to the employees there was
no monetary loss to the petitioner more so, when the 8%
remuneration/mark-up had already been granted to the petitioner. No
evidence was led by the petitioner to prove the loss suffered for
making a claim of damages of rupees one crore. There was no
pleading in the statement of claim for damage of loss of business. The
affidavit filed by the witness of the petitioner stated that the petitioner
had no other client and hence there was no issue of loss occasioned by
termination of the contracts.
The proceedings under Section 34 of the Act are not akin to the
first appeal. There cannot be re-appreciation of evidence; plausible
view calls for no interference; every factual or legal error cannot be a
ground for challenge. The interference is to be made only on the
grounds available in Section 34 of the Act. Reference is made to the
following decisions:
13.1 In Prakash Atlanta (JV) v. National Highways Authority of India,2026 INSC 76 it was held as under:-
“59. (vi) If an arbitral tribunal‟s view is found to be a
possible and plausible one, it cannot be substituted
merely because an alternate view is possible.
Construction and interpretation of a contract and its
terms is a matter for the arbitral tribunal to determine.
Unless the same is found to be one that no fair-minded
or reasonable person would arrive at, it cannot be
interfered with. If there are two plausible
interpretations of the terms of a contract, then no fault
can be found if the arbitrator accepts one such
interpretation as against the other. To be in conflict
with the public policy of India, the award must
contravene the fundamental policy of Indian law,
which makes it narrower in its application.”
13.2 In Ramesh Kumar Jain v. Bharat Aluminium Company Limited (BALCO),2025 INSC 1457 held as under:-
“28. The bare perusal of section 34 mandates a
narrow lens of supervisory jurisdiction to set aside the
arbitral award strictly on the grounds and parameters
enumerated in sub-section (2) & (3) thereof. The
interference is permitted where the award is found to
be in contravention to public policy of India; is
contrary to the fundamental policy of Indian Law; or
offends the most basic notions of morality or justice.
Hence, a plain and purposive reading of the section 34
makes it abundantly clear that the scope of interference
by a judicial body is extremely narrow. It is a settled
proposition of law as has been constantly observed by
this court and we reiterate, the courts exercising
jurisdiction under section 34 do not sit in appeal over
the arbitral award hence they are not expected to
examine the legality, reasonableness or correctness of
findings on facts or law unless they come under any of
grounds mandated in the said provision. In ONGC
14
Limited. v. Saw Pipes Limited, this court held that an
award can be set aside under Section 34 on the
following grounds: “(a) contravention of fundamental
policy of Indian law; or (b) the interest of India; or (c)
justice or morality, or (d) in addition, if it is patently
illegal.”
13.3 In Consolidated Construction Consortium Limited Vs.
Software Technology Parks of India, (2025) 7 SCC 757 it was held
as under:
“46. Scope of Section 34 of the 1996 Act is now well
crystallized by a plethora of judgments of this Court.
Section 34 is not in the nature of an appellate
provision. It provides for setting aside an arbitral award
that too only on very limited grounds i.e. as those
contained in Sub-sections (2) and (2-A) of Section 34.
It is the only remedy for setting aside an arbitral award.
An arbitral award is not liable to be interfered with
only on the ground that the award is illegal or is
erroneous in law which would require re-appraisal of
the evidence adduced before the arbitral tribunal. If
two views are possible, there is no scope for the court
to re-appraise the evidence and to take the view other
than the one taken by the arbitrator. The view taken by
the arbitral tribunal is ordinarily to be accepted and
allowed to prevail. Thus, the scope of interference in
arbitral matters is only confined to the extent envisaged
Under Section 34 of the Act. The court exercising
powers Under Section 34 has perforce to limit its
jurisdiction within the four corners of Section 34. It
cannot travel beyond Section 34. Thus, proceedings
Under Section 34 are summary in nature and not like a
full-fledged civil suit or a civil appeal. The award as
such cannot be touched unless it is contrary to the
substantive provisions of law or Section 34 of the 1996
Act or the terms of the agreement.”
13.4 In The Supreme Court in Sepco Electric Power Construction
Corporation Vs. GMR Kamalanga Energy Ltd., 2025 INSC 1171 held:
“97……..Therefore, it appears that even if the
arbitrator‟s legal or factual reasoning is faulty, the
courts ought to ideally refrain from interfering with an
award until an error of law is evident from the award
itself or in a document that forms an integral
component thereof.”
(emphasis supplied)
The impugned award suffers from no legal or factual error
much less perversity or patent illegality and is not against the public
policy. No case is made out for interference under Section 34 of the
Act. The impugned award is upheld.
The petition is dismissed.
AUGUST 19, 2026
Ch
AVNEESH JHINGAN, J
Reportable: Yes